Authority Intelligence · London data centre outlook

September 2026 edition · data checked 26 August 2026

London Data Centre Outlook: September 2026

A live measure of whether qualifying London data-centre projects are entering and progressing through planning faster or slower than the historical norm. Delivery, power connection and operation are tracked separately.

120

Baseline = 100

June 2026 · latest complete index month

3 new filings + 4 approvals − 1 refusal or withdrawal = 6 net milestones in the trailing year.

September 2026 edition market outlook

London planning momentum remains above normal after a sharp 2025 surge.

The momentum index is 119.5: about 20% above its fixed historical baseline, but down sharply from the early-2026 peak. The index counts the first filing and first decision for each qualifying development, and subtracts first refusals or withdrawals. It does not claim those projects will be built.

Latest momentum index

119.5

Baseline 100 · trailing year to June 2026

Reported connection queue

8+ GW

More than ten times current peak demand

Qualifying planning projects

50

Joined from 566 matching records; 78 uncertain or non-comparable groups withheld

Market summary

London data-centre outlook in five points

Authority’s current public reading of planning activity, delivery evidence and infrastructure pressure. These conclusions use aggregate results so the complete project register can remain private.

  1. 1Planning momentum is 119.5, about 20% above the fixed 2021 to 2024 historical norm.
  2. 2Momentum has fallen sharply from its early-2026 peak of roughly 259 as the large 2025 filing wave leaves the rolling window.
  3. 3Authority is monitoring 50 qualifying projects joined from 566 matching public planning records.
  4. 4Only one monitored project has a verified construction stage and none has independently verified operational status in this planning register.
  5. 5Power remains the main delivery constraint: City Hall reports around 760 MW of current demand and more than 8 GW in the connection queue.

London market answer bank

Direct answers about the London data-centre market

A concise, dated research brief for investors, developers, planners and market researchers. Observed figures are kept separate from Authority’s interpretation so each statement can be quoted with the correct caveat.

London data centresplanning pipelinegrid connectionspower capacityconstruction delivery2026 market outlook

How strong is London data-centre planning activity in 2026?

Authority’s Planning Momentum Index is 119.5 for the trailing year to June 2026. That is 19.5% above the fixed 2021 to 2024 norm of 100, but well below the early-2026 peak of approximately 259.

Observed data

Authority published index data

How large is London’s visible data-centre planning pipeline?

Authority is monitoring 50 qualifying projects joined from 566 matching public planning records. At the August 2026 snapshot, 6 were in planning, 26 were approved, 1 had verified construction evidence, 10 had recorded build completion, 6 were refused or withdrawn and 1 was pre-consent.

Observed data

Authority published pipeline data

What is the main constraint on new London data centres?

Electricity access is the clearest system-wide constraint. City Hall reports approximately 760 MW of current peak data-centre demand and more than 8 GW in the connection queue, over ten times current demand.

Observed data

Greater London Authority

Does planning approval mean a London data centre will be delivered?

No. In Authority’s August snapshot, 26 projects remained at the approved stage, 1 was at verified construction, 10 had a recorded build-complete stage and none had independently verified operational status. Power, finance, construction and commissioning remain separate hurdles.

Observed data

Authority methodology

Where may future London-linked data-centre growth occur?

Authority expects power and suitable land to push more large schemes towards secondary or edge-of-London locations, even if demand remains tied to London. This is a directional interpretation supported by JLL’s evidence that new hyperscale campuses are moving farther from established European hubs.

Authority interpretation

JLL EMEA research

Definitions used on this page

Planning momentum
First qualifying project filings plus first approvals, minus first refusals or withdrawals, measured over a trailing 12-month window.
Qualifying project
A new data centre, conversion or material capacity expansion. Minor equipment works and uncertain record groups are excluded.
Approved
A favourable planning decision is recorded. It does not mean construction, a grid connection or operation has been verified.
Operational verified
Independent public evidence shows the facility is powered and in service, not merely approved or recorded as build complete.

Suggested citation: Authority Intelligence, “London Data Centre Outlook: September 2026,” data checked 26 August 2026; headline index data through June 2026 and pipeline data through August 2026.

Index facts

What this number means

Current score
119.5 · Baseline = 100
Measured period
Trailing 12 months to June 2026, published with a two-month maturity lag
Geography
London, United Kingdom
Definition
First qualifying project filings plus first approvals, minus first refusals or withdrawals, over a trailing 12-month window
Sample
3 first filings + 4 first approvals − 1 first negative outcome = 6 net milestones
Index record updated
2026-08-26

Date guide

How the dates on this page work

Page updated
26 August 2026

The date Authority last checked and refreshed this page, its commentary and monitored project records.

Headline index data through
June 2026

June is the latest complete month used in the headline index. July and August are held back for two months because new planning records can arrive late and would otherwise create a false drop.

Project pipeline data through
August 2026

The project monitor can show newer filings and stage changes. Those faster updates do not enter the headline index until their month has passed the maturity delay.

London data-centre planning momentum

Monthly · trailing 12 months · first filings + first approvals − first refusals/withdrawals · two-month reporting lag

Hover or tap the line · click numbered explanations

Last month

0.0%

+0.0 points · vs May 2026

Last quarter

-40.0%

-79.7 points · vs Mar 2026

Last year

-40.0%

-79.7 points · vs Jun 2025

3002251507502021 to 2024 baseline = 10012Jan 2021Dec 2021Nov 2022Oct 2023Sep 2024Aug 2025Jun 2026

This is a planning-activity index, not an approval probability or a delivery score. A score of 100 equals the fixed 2021 to 2024 average. The latest published month is June 2026 because newer planning records are still incomplete.

View the complete historical data table
Historical observations for London Data Centre Outlook: September 2026
PeriodScoreNet milestonesPositive milestones
Jan 2021119.566
Feb 2021139.477
Mar 2021139.477
Apr 2021139.477
May 2021139.477
Jun 202199.655
Jul 202199.655
Aug 202199.655
Sep 2021159.388
Oct 2021139.477
Nov 2021139.477
Dec 2021119.566
Jan 2022139.477
Feb 2022119.566
Mar 2022139.477
Apr 2022159.389
May 2022159.389
Jun 2022159.389
Jul 2022159.389
Aug 2022159.389
Sep 202299.657
Oct 2022119.568
Nov 202299.657
Dec 202279.746
Jan 202339.825
Feb 202339.825
Mar 202359.836
Apr 202339.824
May 202339.824
Jun 202339.824
Jul 202339.824
Aug 202359.835
Sep 202359.834
Oct 202359.834
Nov 202399.656
Dec 202399.656
Jan 2024139.477
Feb 2024139.477
Mar 202479.745
Apr 202479.745
May 202479.745
Jun 202479.745
Jul 202479.745
Aug 202479.745
Sep 202479.745
Oct 202459.834
Nov 202439.823
Dec 202459.834
Jan 202539.823
Feb 202559.834
Mar 2025139.477
Apr 2025179.399
May 2025199.21010
Jun 2025199.21010
Jul 2025219.11111
Aug 2025199.21010
Sep 2025199.21010
Oct 2025239.01212
Nov 2025219.11111
Dec 2025258.91313
Jan 2026258.91313
Feb 2026258.91313
Mar 2026199.21010
Apr 2026139.478
May 2026119.567
Jun 2026119.567

Live project pipeline

London's discoverable data-centre planning pipeline, month by month

50 qualifying new-build, conversion or material expansion projects found by joining 566 matching Planning London records into one-project-per-row histories. The bars show recorded stages, not estimated progress.

Hover or tap a month for the stage totals

Aggregate pipeline snapshot

50 monitored projects · Aug 26

Public totals only. Authority keeps the complete project register, evidence history and source map private.

Pre-consent
1
In planning
6
Approved
26
Construction verified
1
Build complete
10
Operational verified
0
Refused or withdrawn
6

What changed this month

+1

Newly recorded approval

One monitored project moved from in planning to approved between July and August.

−1

Project still in planning

The in-planning count fell from seven to six as that project moved stage.

0

Net change in monitored population

The register remained at 50 projects; no new construction or operational status was verified.

Pre-consentIn planningApprovedConstruction verifiedBuild complete (planning record)Operational verifiedRefused or withdrawn

This is the discoverable public planning population, not every operating London data centre. Minor equipment works, small refurbishments, consultation records and projects with uncertain identity are withheld. ‘Build complete’ means the planning authority recorded completion of building work; it does not prove the data centre is powered or operational.

26 February 2026

Premier Park moved into approved

OPDC's Planning Committee voted unanimously to grant permission, subject to its legal agreement and conditions.

OPDC committee minutes

15 July 2026

Honey Monster site moved into approved

Ealing's committee granted the hyperscale data-centre application, subject to conditions, its Section 106 agreement and mayoral referral.

Ealing committee minutes

6 August 2026

Heathrow Estate moved into approved

Hounslow's Planning Committee approved the outline application. Construction and power delivery remain unverified.

Hounslow Planning Committee

What changed and why it matters

A sourced monthly briefing around the market measured by this index. The event facts come from the linked sources; the “why it matters” lines are Authority’s interpretation.

Updated for September 2026 edition. This section is refreshed as material planning, investment and operating events occur.

13 August 2026

National Grid launched the North West London Upgrade

The programme includes a new substation, 60 km of new cable and more than 200 km of upgraded overhead line. National Grid says it will enable new connections including five data centres.

Authority reading

This is direct evidence that transmission infrastructure is being built around future computing demand. It improves the medium-term delivery backdrop, but does not guarantee the timing of any individual project.

National Grid

12 August 2026

A major Hounslow scheme highlighted the resource debate

A 12.2-acre data-centre proposal at the Haslemere Heathrow Estate was reported approved after scrutiny of its electricity and water requirements.

Authority reading

A substantive approval adds a positive milestone to planning momentum. Power, water and carbon scrutiny still determine whether that planning progress can become real delivery.

TechRadar Pro

29 July 2026

Ofgem proposed tougher tests for data-centre grid connections

The regulator proposed measures intended to free capacity by tackling speculative projects after contracted demand offers rose sharply, driven largely by data-centre applications.

Authority reading

A planning-approved site without a credible connection route may never reach operation. The reform could make the surviving connection queue more deliverable while removing weaker schemes.

Ofgem

Forward outlook

What Authority expects to matter next

Planning demand remains stronger than the historical norm, but the next phase of the market will be decided less by the number of approvals than by which projects can prove credible power, finance and delivery routes.

Momentum should remain above normal

The recent filing and approval wave is still inside the trailing window, although the index may remain below its early-2026 peak as older filings roll out.

Grid readiness will separate projects

Connection-queue reform and network upgrades should increasingly distinguish deliverable schemes from speculative capacity requests.

More proposals may appear outside western clusters

Charlton and wider European evidence suggest that suitable industrial land and power access may pull future schemes toward secondary locations.

The approval-to-construction gap will remain central

A large approved pipeline is not the same as delivered computing capacity. Construction, power connection and operation must continue to be verified separately.

This is a directional market outlook, not a Forecast Factory-validated probability forecast. Authority has not assigned a probability or claimed a future outcome for the full market.

What London data-centre specialists are saying now

Three expert views published between 6 and 13 August 2026 reinforce the themes visible in Authority’s market monitor: power is shaping location, planning consent is not the same as delivery, and network investment is becoming a decisive part of the pipeline.

Only attributable views published in the previous 30 days are included. Every quote links to its original source.

Assad Noori, Head of Data Centres, Work Dynamics EMEA at JLL

Assad Noori

Head of Data Centres, Work Dynamics EMEA

JLL

Power-led location
The determining factor is increasingly where sufficient power can be secured, rather than simply where demand exists.

Why this matters for the index

This supports Authority’s view that London demand can remain strong while larger projects move towards sites where power and land are easier to secure. It helps explain the geographic shift in the monitored pipeline; it does not prove that any named project will be delivered.

Andrew Eldred, Managing Director at Electrical Contractors’ Association

Andrew Eldred

Managing Director

Electrical Contractors’ Association

Grid and skills
But they must be delivered safely, sustainably and with proper regard for local grid capacity.

Why this matters for the index

This reinforces the gap between planning momentum and real delivery. An approval is one milestone; available grid capacity and skilled construction teams still determine whether a project advances beyond the planning system.

JS

Joe Senior

Project Director

National Grid

Network delivery
The North West London Upgrade is a nationally significant investment that will strengthen the electricity network, unlock new connections, support regional economic growth…

Why this matters for the index

This is concrete evidence that infrastructure is being strengthened around the London market. It makes future connections more credible, but it does not mean every project in Authority’s planning pipeline has secured power.

These are independently published views selected by Authority for their relevance to the index. The quotations do not alter the calculation and are not evidence that any single factor caused an index movement.

London data-centre market briefing

Four developments shaped Authority’s reading of London’s data-centre market over the past two weeks. Together they show strong underlying demand, continued pressure on power infrastructure and growing interest in sites beyond the capital’s established western clusters.

1

National Grid launches a major North West London network upgrade

What changed

On 13 August, National Grid launched its North West London upgrade, including a new substation at Letchmore Heath and wider grid upgrades between Bedfordshire, Hertfordshire and London.

Why it matters

The investment shows both the strength of data-centre demand around London and the barriers previously imposed by power constraints. It does not remove those constraints altogether; it shows the scale of grid investment required to expand computing capacity near established London markets.

Source: National Grid
2

Major data-centre proposal emerges in Charlton

What changed

Plans surfaced for a major data-centre scheme in Charlton. The emerging scheme could provide around 180 MW of computing capacity across 100,000 m² of data-centre floorspace.

Why it matters

The proposal shows continued developer interest beyond London’s established western clusters. It is too early to call this an eastward shift, but well-connected former industrial sites elsewhere in London may become more attractive as land and power constraints affect traditional locations.

Source: Planning application 26/2370/EIA
3

Hyperscale development moves farther from established European hubs

What changed

JLL analysis found that European hyperscale data centres due to open within the next two years will be an average of 175 km from major urban hubs, compared with 46 km for projects delivered between 2022 and 2025. London is among the markets analysed.

Why it matters

Hyperscale projects are becoming less tied to major urban centres as developers seek locations where land and power are easier to secure. For London, future demand may increasingly support development in surrounding and secondary markets rather than within the capital itself.

Source: JLL EMEA research
4

AWS expands its London cloud region

What changed

On 19 August, AWS added a fourth Availability Zone to its Europe (London) Region, increasing cloud capacity for higher AI and machine-learning workloads.

Why it matters

The expansion is clear evidence that demand associated with the London market remains strong, particularly as AI workloads grow. AWS does not disclose the physical location of the new infrastructure, so this is a stronger signal of underlying demand than of development patterns within London itself.

Source: AWS

Research and interpretation by Authority.inc. This commentary adds market context and does not change the index calculation.

An expert reading of the change

From a planning perspective, Isabella gives most weight to the number and maturity of genuine development proposals entering the system. A filing wave can lift momentum before it says anything about construction. Power availability remains crucial to delivery, but it is deliberately outside this planning-activity score.

This is a planning and development view, not specialist data-centre investment or engineering advice.

1

A wave of new project filings

Several genuine capacity projects entering planning close together directly lifts this index. It shows greater development activity, not guaranteed delivery.

Strong effect
2

Projects moving from filing to approval

Later approvals add a second milestone for a project and show that part of the pipeline is progressing, although every later delivery step still has to be completed.

Medium effect
3

Electricity constraints

Power availability can decide whether a data centre is ultimately delivered, but it does not change the count of planning filings and decisions measured here.

Outside this index

Planning stage matters

A later-stage application may face a narrower planning question, but it is not automatically low-risk. Whether consent is pursued in one detailed application or through allocation, outline consent and reserved matters, all required steps still have to be completed.

This is professional market interpretation of the observed movement. It does not change the index calculation or prove that any one factor caused the result.

Momentum is above normal, but well below its recent peak.

The index reached about 259 in early 2026 as a large 2025 filing wave moved through planning. It fell to 119.5 by June as older filings left the annual window faster than new ones replaced them. That is still about 20% above the historical baseline.

1,289 MW

Reported secured capacity

Site, permission and power reported secured

Planning evidence

Selected projects from Authority’s private register

These five public examples show how Authority monitors named projects without publishing the complete 50-project intelligence register. One row represents one qualifying capacity project rather than every planning document; uncertain, minor-work and non-comparable record groups remain withheld.

East Havering Data Centre Campus

North Ockendon · Havering

Pre-consent

600 MW announced; a long phased build remains subject to approval.

Source
Heathrow Estate Data Centre

Silver Jubilee Way · Hounslow

Committee approved

48 MW IT load. Operator, detailed design and power delivery remain outstanding.

Source
Former Honey Monster Factory

Southall · Ealing

Committee approved

Granted subject to conditions, a Section 106 agreement and Stage 2 mayoral referral.

Source
Hayes Bridge Data Centre Campus

Uxbridge Road · Hillingdon

Details pending

Main hybrid permission exists; Phase 2 details and technical conditions remain under review.

Source
Premier Park Road Data Centre

Park Royal · OPDC

Permission granted

Construction, environmental and fibre-condition details are still being discharged.

Source

How to read this benchmark

  1. Join related applications and documents into one project before calculating the index.
  2. Count each project's first qualifying filing and first approval once; subtract its first refusal or withdrawal once.
  3. Use a trailing 12-month window and publish monthly with a two-month maturity lag.
  4. Rebase the fixed average monthly net milestone count during 2021 to 2024 to 100; do not cap the index at 100.
  5. Keep planning approval separate from later construction, electricity connection and operational delivery.

Questions about this index

How active is London data-centre planning in the latest published period?

The latest Planning Momentum Index is 119.5 for the trailing 12 months to June 2026. That is about 20% above the fixed 2021 to 2024 baseline of 100.

Is London data-centre planning momentum improving?

Momentum remains above its historical norm but has fallen sharply from its early-2026 peak of about 259. Older 2025 filings left the rolling window faster than new milestones replaced them.

Does the index cover every London data centre?

No. It covers qualifying new-build, conversion and material-expansion projects found in public planning records. Minor equipment works, small refurbishments and projects with uncertain identity are withheld.

Does planning approval mean a data centre will become operational?

No. Planning approval does not prove that construction, a grid connection, commissioning or operation will follow. Authority tracks those stages separately when public evidence is available.

What does Authority expect for London data-centre development in late 2026?

Authority expects power access and delivery readiness to remain the main constraints while planning activity stays above its historical norm. This is a directional interpretation, not a probability forecast for the whole market.

What is the outlook for the London data centre market in 2026?

Demand and planning activity remain strong, but power access and delivery readiness are the main constraints. Grid upgrades support future capacity, while Ofgem's proposed reforms may remove speculative connection requests. Planning approval alone is not evidence that a site will become operational.

What does the London Data Centre Planning Momentum Index measure?

It measures how much qualifying project activity is moving through London's planning system. Each project's first filing and first approval add one; its first refusal or withdrawal subtracts one. Repeat documents for the same development do not create extra projects.

What does a score above 100 mean?

A score of 100 is the fixed average level of net planning milestones during 2021 to 2024. A score of 120 means activity was about 20% above that norm. It is not a percentage and has no maximum of 100.

Why does the latest point stop two months behind today?

Very recent planning records are incomplete. Waiting two months prevents missing updates from creating a false fall in the index.

Are Green Belt and later-stage applications directly comparable?

They are included under the published rule, but they can carry very different planning risk. The page identifies this mix problem and does not claim that every application is equally difficult.

Can I reuse the historical data?

Yes. Machine-readable JSON and CSV files are linked in the index facts box. Please cite Authority Intelligence and the underlying Planning London Datahub.

Why does Authority not publish the complete project register?

The public page provides aggregate pipeline totals, selected named examples, methodology and source evidence. The complete project register, entity matching, evidence history and monitoring system are proprietary Authority intelligence and are available through the private monitor.