Authority Intelligence · London data centres
Verified 24 August 2026
London data-centre planning approvals
The verified historical share of comparable, substantive London data-centre applications receiving a favourable planning decision.
Out of 100
Q4 2024
14 of 16 resolved applications were approved.
Historical approval rate
Mature trailing 24-month cohorts · updated quarterly
Hover or tap the line · click numbered explanations
Up 9.4% over the last year
+7.5 index points · versus Q4 2023
This is a small historical planning sample, with a likely range of roughly 64%–97%. It does not measure construction, power connection or operational delivery. Markers are limited to real-world explanations supported by project or policy evidence; likely contributors are labelled separately.
Market context
Demand is large. Delivery remains uncertain.
London's data-centre market has strong demand and a substantial connection queue, but planning approval is only one gate. Power, construction and customer delivery must be verified separately.
Operating London sites
City Hall market snapshot, June 2026
Current peak demand
City Hall market snapshot, June 2026
Connection queue
More than ten times current demand
Reported secured capacity
Site, permission and power reported secured
Underlying evidence
Current projects being monitored
One row represents one real project, rather than every planning document. This is a transparent public watchlist, not yet a complete London delivery population.
North Ockendon · Havering
600 MW announced; a long phased build remains subject to approval.
SourceSilver Jubilee Way · Hounslow
48 MW IT load. Operator, detailed design and power delivery remain outstanding.
SourceSouthall · Ealing
Granted subject to conditions, a Section 106 agreement and Stage 2 mayoral referral.
SourceUxbridge Road · Hillingdon
Main hybrid permission exists; Phase 2 details and technical conditions remain under review.
SourcePark Royal · OPDC
Construction, environmental and fibre-condition details are still being discharged.
SourceMethod
How to read this benchmark
- Include full, outline and reserved-matters applications with a recorded final decision.
- Exclude consultations, condition discharges, amendments, adverts and administrative records.
- Use mature trailing 24-month cohorts and publish quarterly so overlapping monthly observations are not presented as independent evidence.
- Keep planning approval separate from later construction, electricity connection and operational delivery.